The answer
Yes. The municipality must issue a Certificate of Occupancy before the CRA will conduct its pre-licensure inspection. The CRA also notifies the local government of a pending application and allows 14 to 21 days for the municipality to report noncompliance, so the municipal permitting sequence gates the state's final step.
Sequence the build-out around this gate
Because the CRA inspection cannot happen before the Certificate of Occupancy, build-out schedules should treat local plan review, permitting and final inspection as the critical path, not the CRA application itself. A completed CRA application sitting behind an unfinished building or an unresolved permit issue accomplishes nothing until the municipality signs off.
Sources
Where these figures come from
Go deeper
Related pages on this site
More michigan licensing & zoning answers
- How much does it cost to open a dispensary in Michigan?
- How much is a cannabis license in Michigan?
- Which Michigan cities allow marijuana dispensaries?
- What is a green zone and how do I find one in Michigan?
- What is the difference between opting in and opting out in Michigan?
- How far does a dispensary have to be from a school in Michigan?
Last updated
Cannabis practice
How C3 CRE brokers licensed cannabis real estate, and why marketplaces don't close these deals.
ReadMichigan cannabis real estate
Opt-in vs opt-out, the 1,000-foot buffer, municipal authority, and current CRA market data.
ReadMichigan license types
Every adult-use license with annual fee, plant limit and the real estate it actually requires.
ReadMichigan distressed & receivership
The 24% wholesale tax, the TerrAscend receivership, and why licenses don't transfer with the building.
ReadCannabis site selection guide
Power, dehumidification, structure, water, extraction classification, zoning and timeline.
ReadFlorida cannabis & hemp
Why vertical integration removes the brokerage market — and why hemp is the real Tampa Bay story.
ReadNext step
Apply this to your deal
Tell us the jurisdiction, licence type and building profile. We confirm the ordinance and licence position with the municipality and the CRA, then show you what survives it.
Last updated