The answer
Verify electrical service and utility upgrade capacity, clear height and roof loading against the mechanical design, water and drainage infrastructure, hazardous classification feasibility if extraction is planned, and zoning: permitted versus conditional use, buffer measurement method, and remaining license capacity in that district before treating any warehouse as a viable site.
Range reflects C3's Michigan transaction experience, not a published dataset.
Sequence diligence, don't run it all at once
Zoning and utility diligence should run first and in parallel, because they are pass/fail gates that make everything else irrelevant if they fail. Only after a parcel clears opt-in status, permitted-use zoning and a utility capacity letter does it make sense to spend money on detailed mechanical and structural engineering.
Go deeper
Related pages on this site
More facilities & real estate answers
- How much power does a cannabis grow facility need?
- What ceiling height do I need for an indoor cannabis grow?
- What is C1D1 and do I need it for extraction?
- How much does a dispensary build-out cost?
- Should I buy or lease my cannabis property?
- What is a cannabis sale-leaseback and why do operators do them?
Last updated
Cannabis practice
How C3 CRE brokers licensed cannabis real estate, and why marketplaces don't close these deals.
ReadMichigan cannabis real estate
Opt-in vs opt-out, the 1,000-foot buffer, municipal authority, and current CRA market data.
ReadMichigan license types
Every adult-use license with annual fee, plant limit and the real estate it actually requires.
ReadMichigan distressed & receivership
The 24% wholesale tax, the TerrAscend receivership, and why licenses don't transfer with the building.
ReadCannabis site selection guide
Power, dehumidification, structure, water, extraction classification, zoning and timeline.
ReadFlorida cannabis & hemp
Why vertical integration removes the brokerage market — and why hemp is the real Tampa Bay story.
ReadNext step
Apply this to your deal
Tell us the jurisdiction, licence type and building profile. We confirm the ordinance and licence position with the municipality and the CRA, then show you what survives it.
Last updated